Downtown summer construction update
Posted on:
We have some great news for the downtown core! We are paving the gravel sections soon to minimize impacts on local businesses. Paving will get downtown ready for a fun and prosperous summer 2024. All downtown businesses in construction areas are open.
Centennial Street Redevelopment
- Before 1913 Days: A temporary layer of asphalt on the 50 Avenue and Centennial Street intersection, weather permitting. This will keep downtown flowing smoothly through the summer months
- Ask Centennial Street questions here
50 Avenue Redevelopment
- Before Canada Day: A temporary layer of asphalt on 50 Avenue (49 Street to Centennial Street), weather permitting. This will keep downtown flowing smoothly through the summer months
- Completing concrete work, including curbs, flower beds, and the concrete pad in front of the Library
- Ask 50 Avenue questions here
Learn more
- Timelines are under project phases in Centennial Street Redevelopment and 50 Avenue Redevelopment