We are pleased to announce that the Rotenone application is complete. The last pond water test showed that the rotenone concentration is below the detectable limit. We have received approval from Alberta Environment and Protected Areas that it is now safe to open the flow of the pond water into the stormwater system. Over the next couple of days, our team will be onsite removing the fencing and plugs. You may see some heavy equipment in action for this work. Repairs to any minor rutting caused by the equipment will be completed in the spring.
November 2024
- November 6 - 7: Unplugging the pond so it once again flows into the stormwater system
- Fence removal
- New signage is going up that includes messaging about abandoning pets
Spring 2025
- Fill in any ruts with grass seed