Town of Sylvan Lake Festival Street Expansion Project Underway!

Posted on:

Weather permitting, construction begins Monday, July 11 on the Festival Street Expansion Project.

  • Completion is expected by October 2022
  • Most construction is scheduled between 7:00 AM and 7:00 PM
  • Some occasional work on Sunday is required

This phase of the project includes:

  • Excavation and removals
  • ATCO gas line work
  • Water main replacement
  • Sanitary service replacements
  • Installation of electrical conduit and streetlights
  • Gravel road structure
  • Asphalt paving
  • Concrete sidewalks and crosswalks
  • Landscaping
  • Line marking
  • Installation of a public art component

The next phase begins in 2023:

  • Second layer of asphalt
  • Addition of street furniture

Background information:

For more information:

Jared Waldo, Communication Officer

Town of Sylvan Lake | Brilliant all year.

T 403 887 2141 Ext. 244

OR

Amanda Mercer, Economic Development Officer

Town of Sylvan Lake | Brilliant all year.

T 403 887 2141 Ext. 226

Related Posts